Pilbara Minerals Announces Regarding First Load Commissoning for Crusher Commences

Pilbara Minerals Limited advised that ore load commissioning has begun through the crushing facilities at its 100%-owned Pilgangoora LithiumTantalum Project in WA.

The Pilgangoora crusher facilities have been provided under a build own operate contract by Crushing Services International (a division of Mineral Resources Limited) and their safe and reliable work during construction of the crusher facilities has been welcomed by the Pilbara Minerals team. Their experience in crushing and processing spodumene and strong culture of delivery is a great value add for Pilbara as it continues to de-risk and deliver the overall concentrator program.

In parallel with the commencement of load commissioning of the crusher, construction of the overall processing plant for Pilgangoora is progressing towards completion with subsets of the plant’s circuits being completed daily, in preparation for the commencement of commissioning of the main Pilgangoora concentrator in the coming weeks.

The Company remains on track to deliver the first concentrate from the processing plant by the end of June 2018.


Disclaimer

The advice given by Kalkine Pty Ltd and provided on this website is general information only and it does not take into account your investment objectives, financial situation or needs. You should therefore consider whether the advice is appropriate to your investment objectives, financial situation and needs before acting upon it. You should seek advice from a financial adviser, stockbroker or other professional (including taxation and legal advice) as necessary before acting on any advice. Not all investments are appropriate for all people. Kalkine.com.au and associated websites are published by Kalkine Pty Ltd ABN 34 154 808 312 (Australian Financial Services License Number 425376). The information on this website has been prepared from a wide variety of sources, which Kalkine Pty Ltd, to the best of its knowledge and belief, considers accurate. You should make your own enquiries about any investments and we strongly suggest you seek advice before acting upon any recommendation. Kalkine Pty Ltd has made every effort to ensure the reliability of information contained in its newsletters and websites. All information represents our views at the date of publication and may change without notice. To the extent permitted by law, Kalkine Pty Ltd excludes all liability for any loss or damage arising from the use of this website and any information published (including any indirect or consequential loss, any data loss or data corruption). If the law prohibits this exclusion, Kalkine Pty Ltd hereby limits its liability, to the extent permitted by law to the resupply of services. There may be a product disclosure statement or other offer document for the securities and financial products we write about in Kalkine Reports. You should obtain a copy of the product disclosure statement or offer document before making any decision about whether to acquire the security or product. The link to our Terms & Conditions has been provided please go through them and also have a read of the Financial Services Guide. On the date of publishing this report (mentioned on the website), employees and/or associates of Kalkine Pty Ltd do not hold positions in any of the stocks covered on the website. These stocks can change any time and readers of the reports should not consider these stocks as advice or recommendations.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

w

Connecting to %s